Comments on: How status codes help in BIM Coordination https://bimcorner.com/how-status-codes-help-in-coordination-process/ Everything you want to know about Building Information Modeling Sun, 07 Aug 2022 07:27:52 +0000 hourly 1 https://wordpress.org/?v=6.3.1 By: ahmed elnafa https://bimcorner.com/how-status-codes-help-in-coordination-process/#comment-709 Sun, 07 Aug 2022 07:27:52 +0000 http://bimcorner.com/?p=14593#comment-709 is there relation between codes of elements ( S0 , S1 , S2 , etc. ) and project stages especially design stages 

could you clarify with an example of a digital production manual and what requirements should be on it?

]]>
By: Ignacy Lozinski https://bimcorner.com/how-status-codes-help-in-coordination-process/#comment-405 Sat, 03 Apr 2021 10:59:40 +0000 http://bimcorner.com/?p=14593#comment-405 In reply to Juan Hoyos.

Good to know Juan, that you find our blog useful. We are happy to help:) I am still in the production phase of BBC. I think it will be ready in June, but I am not sure if I will sell it then or wait until September for release. Always vacation months are rather “quiet”. So I do not want to release in it this period. Anyway, I will keep you informed 🙂 Thanks for the comment, and wish you luck with your project.

Cheers,
Ignacy

]]>
By: Juan Hoyos https://bimcorner.com/how-status-codes-help-in-coordination-process/#comment-404 Thu, 01 Apr 2021 00:57:57 +0000 http://bimcorner.com/?p=14593#comment-404 In reply to Ignacy Lozinski.

Hi again Ignacy 🙂

Your answer was pretty clear, thank you so much!. I am into a coordination of a medium size model but very complex in terms of MEP, so I am implementing this status codes and was passing a BCF with all the elements that needed to be checked as coordinated, but was not sure if it makes sense to be done that way. Now, with your answer, I know its ok.

Again, thank you so much! I am loving this blog. Also, I am looking forward to get BBC, any release date planned?

]]>
By: Ignacy Lozinski https://bimcorner.com/how-status-codes-help-in-coordination-process/#comment-402 Wed, 31 Mar 2021 05:42:31 +0000 http://bimcorner.com/?p=14593#comment-402 In reply to Juan Hoyos.

Hi Juan,
Thanks for a good words 🙂 As you wrote, all SC10 are predefined, SC 20 status is set by each discipline when their model goes through internal check. I worked on projects where there was a BIM Specialist responsible for each discipline who set those statuses whenever their model (part of the model) was ready.

All statuses are set in modeling tool. BIM Coordinator do his check, if everything goes ok, then BC inform BIM Specialist for each discipline to change the Status Code, to a proper one. If there are some elements which need correction then Status Code is not changed and wait for correction.

I hope I clarified it. Cheers

]]>
By: Juan Hoyos https://bimcorner.com/how-status-codes-help-in-coordination-process/#comment-401 Tue, 30 Mar 2021 17:49:23 +0000 http://bimcorner.com/?p=14593#comment-401 Hi Ignacy! Loved the post 🙂 I have two questions if you can help me:

  1. Who in the team should set the SC-20 element code? Because as I understand all elements have SC-10 predefined and the SC-30 is set by the BIM Coordinator, is that right?
  2. In which software are the codes set? My guess is SC-10 and SC-20 are both set in the modeling software, but the SC-30?

Thank you so much for sharing this information!

]]>